Challenges and Benefits of 4D Modeling on the Walt Disney Concert Hall Project

TitleChallenges and Benefits of 4D Modeling on the Walt Disney Concert Hall Project
Publication TypeWorking Paper
Year of Publication2001
AuthorsHaymaker, J, Fischer, M
IssueWP064
Date Published01/2001
PublisherCIFE
Publication Languageeng
Keywords4-D, Center for Integrated Facility Engineering, CIFE, Construction, Process Modeling, Scheduling, Stanford University
AbstractThe goal was to test the applicability and usefulness of 4D modeling and of the 4D prototype software developed between CIFE and Walt Disney Imagineering on a complex project like the Walt Disney Concert Hall project in Los Angeles. The 4D models built with the help of CIFE helped the construction team find many schedule inconsistencies, resolve access, scaffolding and hoisting issues for the exterior and interior construction in a timely manner, inform more stakeholders of the approach to construction and of the schedule, and engage subcontractors in the scheduling process.
URLhttps://purl.stanford.edu/fw529qc5108
PDF Linkhttps://stacks.stanford.edu/file/druid:fw529qc5108/WP064.pdf